Monticello SLR application docketed

March 9, 2023, 12:02PMNuclear News
The Monticello nuclear power plant. (Photo: NRC)

The Nuclear Regulatory Commission has accepted for review Northern States Power Company’s subsequent license renewal application for its Monticello nuclear power plant. A notice of the agency’s decision, along with information on requests for a hearing in the matter, was published in the March 3 Federal Register.

Belarus’s first nuclear reactor connects to grid

November 4, 2020, 6:57AMNuclear News

The Belarusian nuclear power plant. Photo: Rosatom

Belarus on November 3 became the latest nation to begin generating electricity with nuclear energy when Unit 1 of the Belarusian nuclear plant was connected to the country’s power grid.

The Belarusian construction project, located in the Grodno region of Belarus, features twin 1,109-MWe pressurized water reactors, supplied by Rosatom, Russia’s state-owned nuclear energy corporation. The units are VVER-1200 Generation III+ designs, model AES 2006. Just last week, a VVER-1200 was connected to the Russian grid at the Leningrad plant.

The start-up program for Unit 1 began on August 7, when the first fuel assembly with fresh nuclear fuel was loaded into the reactor, according to a Rosatom press release. The reactor achieved first criticality on October 11.

Once fully completed, the plant is expected to supply approximately 18 billion kWh of low-carbon electricity to the Belarus national grid every year, Rosatom said.